After the drawings are approved or the permit is issued, your wishes may change: an extra room, moving the kitchen, changing the facade, or a larger annex. This is normal in building projects that last months. But the key question is: does the change need re-approval? A wrong answer can mean a building that differs from its permit, and a problem that surfaces at the occupancy certificate or sale. This guide explains the general rule, examples of each type of change, the requirements of the add and modify building components service, the difference between changing before and after the permit, and why you should not change things on site directly.

The General Rule

If the change alters the building components in the permit (adding, removing or modifying a component, or changing areas, floors or use), it needs a regulatory route. Balady states that changes to a building permit after issue, such as adding a floor or removing an annex, are made through the add and modify building components service.

Examples

ChangeLikely route
Changing the internal layout without affecting areas or structural elementsAmending the construction drawings with the office, which decides whether it affects the approved set
Adding a room, annex or floorAdd and modify building components
Changing the useDepends on the requirements, usually modifying components
Changing the facade designDepends on the scope of change and identity requirements
Enlarging openings or removing load-bearing wallsNeeds a structural study and a regulatory route

For adding annexes and floors read: Adding an annex or rooftop room and Structural assessment for an additional floor.

Requirements of the Add and Modify Building Components Service

  • Contracting an engineering office.
  • Paying the service fee.
  • An existing building permit.

See our addition and modification permit service, and read: Modifying building components.

Before or After the Permit?

TimingWhat happensEase
During designThe office amends the drawings directlyEasiest and cheapest
During reviewThe change is included in the response to commentsEasy, with possible delay
After the permit is issuedThe add and modify building components serviceNeeds a procedure and fees
After construction without amendmentStatus correction, and fines may applyHardest

Why Not Change Things on Site Directly?

Because construction that departs from the drawings surfaces at the occupancy certificate, complicates sale, and may expose you to fines. Read: Made changes without amending the drawings? and Reasons the occupancy certificate is rejected.

Tips to Reduce Changes

  • Use 3D design before approval.
  • Discuss future needs early.
  • Have the supervisor document any on-site change request and refer it to the office.

Frequently Asked Questions

Can I make changes before the permit is issued?

Yes, changing before issue is easier; the office amends it within the review round.

Do the structural drawings need amending too?

If the change affects elements or loads, yes.

Does changing colours and finishes need a permit?

Interior finishes usually do not, but the facade may be subject to urban identity requirements. Read: The facade renovation permit.

Who is responsible for an unapproved change?

The owner, contractor and supervisor, each according to their role. Read: Supervisor and contractor responsibility.

How long does modifying the permit take?

It depends on the scope of the change, the quality of the drawings and review rounds.

How Abak Engineering Consultancy Helps

Abak is an accredited engineering office in Riyadh that studies the requested change, determines whether it needs re-approval, prepares the amended architectural and structural drawings, and obtains the addition and modification permit. Contact us.

Regulatory information is based on the Balady platform and the Ministry of Municipalities and Housing, and procedures may be updated by the competent authority. Last reviewed: October 2026.