Quick answer: An owner cannot issue a building permit on the Balady platform by themselves. They authorise an accredited design engineering office, which accepts the authorisation from its "Balady Business" account, selects the survey report, prepares the architectural and structural designs, and submits the application to the technical inspector until the permit is issued. The office you choose determines how fast your permit comes through and the quality of your building.
In this article from Abak Engineering Consultancy we explain, step by step and according to Balady's official procedures, the engineering office's role in obtaining a building permit, the difference between the types of offices required, how to verify that an office is genuinely accredited, and what your contract with it should include.
Why do you need an engineering office to obtain a building permit?
According to the description of the building permit issuance service on Balady, the permit owner or their representative authorises a design engineering office to issue the permit. The office then logs in to "Balady Business" with its account, accepts the authorisation and starts the application. The permit path is designed to pass through the engineering office; there is no route for the owner to submit drawings themselves.
The Implementing Regulations of the Municipal Licensing Procedures Law define the engineering office as an engineering office accredited by the ministry according to its approved requirements and conditions. So not every design office qualifies; it must be accredited to work on the platform.
What exactly does a building permit office do?
Based on Balady's procedures, these are the design office's tasks:
- Accepting the owner's authorisation on Balady Business and starting the service request.
- Selecting the survey report (survey decision) for the plot. If you do not have one, the office issues it first. See our survey report service.
- Preparing the architectural and structural engineering designs in line with the Saudi Building Code and the area's municipal requirements (setbacks, ratios, heights).
- Completing the application data and attaching the required files on the platform.
- Agreeing to the municipal undertakings on behalf of the project.
- Sending the application to the technical inspection company, which reviews the drawings and designs as part of the hidden defects insurance procedure.
- Addressing the technical inspector's comments and resubmitting until approval.
- After approval a payment invoice is issued, and after payment the permit is issued.
Design office vs. supervising office: what is the difference?
Building permit requirements on Balady include contracting a design engineering office to design the drawings and contracting a supervising engineering office and a building contractor. So there are two different roles:
| Item | Design office | Supervising office |
|---|---|---|
| When does it work? | Before the permit | After the permit and during construction |
| Main task | Preparing drawings and submitting the application on Balady | Ensuring construction matches the approved drawings |
| Outputs | Approved drawings + building permit | Construction reports and notifications, then the occupancy certificate path |
| Link to the occupancy certificate | Indirect | Direct: for new applications the occupancy certificate is issued through the supervising office after construction reports are submitted |
The same office can be both designer and supervisor, which makes communication easier because the person who designed the building follows its construction. Read more in Engineering supervision office: role and responsibilities.
Requirements the owner prepares before contacting the office
According to the Balady service page, building permit requirements are:
- An updated electronic title deed from the Ministry of Justice, a housing contract or an investment contract.
- A survey decision for construction purposes.
- Contracting a design engineering office to design the drawings.
- Contracting a supervising engineering office and a building contractor.
- Hidden defects insurance for the building.
If your deed is paper-based, start by updating it to an electronic deed. See our guide to updating paper deeds to electronic deeds.
How do you verify that an engineering office is accredited?
Before signing, check three things:
- Licence from the Saudi Council of Engineers: engineering offices and firms are licensed under the "Standards for Practising Engineering Professions and Licensing Conditions" issued by the Council in coordination with the Ministry of Commerce, and the office must stay within the disciplines approved in its licence.
- Presence on Balady: when you click "Request a contract with an office" on Balady, the system redirects you to the Saudi Council of Engineers, and only engineering offices appear in the search results. You can also use Balady's engineering offices enquiry service.
- Disciplines required for your project: a residential villa differs from a commercial building or factory. Make sure the office has accredited engineers in architecture, structure, electrical and mechanical.
For detailed selection criteria read: Engineering consulting offices: types and how to choose.
What should your contract with a building permit office include?
A clear contract protects you from surprise costs. Make sure it includes:
- A detailed scope of work: does it include the survey report? Electrical and mechanical drawings? Safety drawings? Interior design?
- The number of design revisions allowed before submission.
- Responsibility for addressing technical inspector comments at no extra cost.
- Separation of municipal fees from office fees; the municipal fee is paid directly to the municipality. See the official building permit fees.
- An estimated timeline for each stage (design, submission, approval).
- Delivery of drawing files to you in usable formats (PDF and DWG).
How long does a permit take through an engineering office?
The duration depends on three factors: readiness of the documents (deed and survey decision), design preparation time, and the number of comment rounds with the technical inspector. An experienced office reduces the last factor because it designs to the requirements from the outset. Balady notes that published service times do not include the time taken to complete missing items or processing by third parties.
Common mistakes when choosing an engineering office for a building permit
- Choosing only the cheapest: weak drawings mean repeated comments, then changes during construction that cost many times the difference.
- Dealing with an agent instead of an office: an agent has no authority to submit on Balady Business and will eventually deal with an office you do not know.
- Not reviewing the drawings before submission: ask for a review session on the architectural drawings before approval, as changes after the permit require the "Add and modify building components" service. Details in Building permit modification cost.
- Overlooking supervision: some owners think the office's role ends with the permit, while the occupancy certificate depends on the supervising office's reports.
The permit journey with an engineering office: an approximate stage timeline
There is no single official duration, but this is the order in which the stages actually run, and who owns the time at each stage:
| Stage | Who works? | What speeds it up? |
|---|---|---|
| 1. Preparing the deed and survey decision | Owner and office | An updated electronic deed and immediate authorisation of the office |
| 2. Gathering requirements | Owner and office | A clear list of rooms, annexes and parking |
| 3. Preliminary and final design | Office | Quick owner decisions on the options |
| 4. Structural and MEP design | Office | Soil investigation results ready |
| 5. Submission on Balady Business | Office | Complete files the first time |
| 6. Technical inspection and insurance | Technical inspector, contractor and insurer | A code-compliant design and a contractor ready to apply for the policy |
| 7. Payment and issuance | Owner | Paying the invoice as soon as it is issued |
Warning signs when choosing a building permit office
- "We'll get your permit in two days" regardless of the file's condition: the office does not control the technical inspector's time or the insurance readiness.
- Refusing to write down the scope of work: any serious office puts in writing what it will deliver.
- No named engineer responsible for your file to communicate with.
- Combining government fees with professional fees in one figure without breakdown.
- Asking for your National Single Sign-On (Nafath) password: authorisation is done from your own account, and nobody is entitled to ask for your login details.
What does an engineering office provide beyond the permit?
A good office's role does not end at printing. After the permit you usually need:
- Detailed construction drawings for the contractor, more precise than the permit drawings.
- Bills of quantities to price and compare contractor quotations.
- Engineering supervision and submission of construction reports.
- Handling any change that arises during construction through the correct service.
- The occupancy certificate path at the end of the project.
Ask the office from the start which of these services are in its quotation and which need a separate contract.
Terms you need to know
| Term | Short meaning |
|---|---|
| Balady | The unified digital platform for municipal services, replacing visits to municipal offices for construction licences |
| Balady Business | The platform interface for engineering offices and contractors, from which the office submits applications |
| Survey decision (survey report) | A document defining the plot's boundaries and dimensions on the ground, issued for a specific purpose such as construction or demolition |
| Design office | The engineering office that prepares the designs and submits the permit application |
| Supervising office | The office that verifies construction matches the drawings and submits construction reports |
| Technical inspector | A body that reviews drawings as part of the hidden defects insurance procedure and issues the safety confirmation certificate at the end |
| Hidden defects insurance | A policy covering defects that appear after construction and were not visible at handover |
| Occupancy certificate | The building completion certificate confirming the building's actual completion |
Abak Engineering Consultancy: an engineering office for building permits in Riyadh
We handle the entire building permit file: the survey report, architectural, structural, electrical and mechanical design, submission on Balady, and following up with the technical inspector until the permit is issued, then engineering supervision until the occupancy certificate. We set out the scope of work, our fees and the municipal fees in writing before starting.
Get started: call 0531145777 or explore our services. To learn the authorisation steps on the platform, read Authorising an engineering office on Balady.
Frequently asked questions
Can I obtain a building permit without an engineering office?
No. The building permit service on Balady requires authorising a design engineering office that prepares the designs and submits the application from its Balady Business account.
Must the design office also be the supervising office?
Not necessarily, but contracting a supervising office is a permit requirement. Choosing the same office for both roles makes follow-up easier.
How do I know the office is accredited?
Check its licence with the Saudi Council of Engineers and its presence in Balady's engineering offices enquiry service.
Do the office's fees include municipal fees?
Usually not. The municipal fee is paid via a Balady payment invoice, and office fees are a separate item in the contract.
Is an engineering office entitled to ask for my Nafath password?
No. Authorisation is done from your own account, and the office does not need your login details.
Is the engineering office responsible for technical inspector delays?
The office is responsible for the quality of the file and for addressing comments promptly; the review time itself lies with the technical inspector.