Quick answer: An engineering supervision office is responsible for verifying that the building is constructed according to the drawings approved in the permit. Contracting one is a requirement for issuing a building permit on Balady. It follows construction stages and submits construction reports (construction notifications), and for new permits the occupancy certificate is issued through the supervising office once these reports are complete.

Many owners see engineering supervision as a formality added to complete the permit. In reality it is the line of defence between you and construction errors, and the gateway to the building completion certificate. In this guide from Abak Engineering Consultancy we explain engineering supervision, its role and responsibilities according to official procedures.

Is engineering supervision mandatory?

Yes for building permits. The requirements of the building permit issuance service on Balady include contracting a supervising engineering office and a building contractor, alongside contracting the design office and hidden defects insurance. In the Add and modify building components service, the owner selects the supervising office or retrieves it from the insurance. So the supervisor is present in the building's life cycle from permit to occupancy.

What does an engineering supervision office do?

Before construction starts

  • Reviewing the approved drawings and confirming they are complete for construction.
  • Reviewing the contractor's contract and schedule.
  • Handing over the site and setting levels according to the survey report.

During construction

  • Excavation and foundations: checking excavation levels, soil investigation results and footing reinforcement before casting.
  • Concrete frame: inspecting reinforcement and formwork before casting columns, beams and slabs.
  • Materials: ensuring materials match specifications, and following concrete tests.
  • MEP works: installations before they are closed up.
  • Waterproofing and finishes.
  • Submitting construction reports (construction notifications) on the platform at each stage.

After construction

  • Completing reports so the occupancy certificate path starts.
  • Once requirements are complete, the technical inspector issues the safety confirmation certificate.
  • After occupancy, the building compliance certificate is issued proactively and the hidden defects insurance policy is activated.

Details of this stage in Building completion certificate requirements and steps.

Supervising office, design office, contractor: who is responsible for what?

PartyMain responsibility
Design officeDrawings, designs and permit issuance
ContractorConstruction, and applying for the hidden defects insurance policy
Supervising officeMatching construction to the drawings and submitting construction reports
Technical inspectorReviewing designs for insurance purposes, and confirming safety at the end

The design office can also be the supervisor, which makes answering site questions easier because the designer knows the details of its calculations. Read Engineering office for building permits.

Why engineering supervision protects you

  • Concrete errors are hard to fix: discovering missing reinforcement before casting costs minutes; after, it may cost re-construction.
  • Hidden defects insurance: covers defects that appear after construction and were not visible at handover, and good supervision reduces their likelihood in the first place.
  • The occupancy certificate: without complete supervision reports, the occupancy path does not start for new permits.
  • Stage documentation: a reference in any dispute with the contractor.

What does an engineering supervision contract include?

For government entities, there is an approved model contract for consulting engineering services (supervision) issued by Council of Ministers Resolution No. 259. For private projects, make sure your contract defines:

  • Scope of supervision: partial (specific stages) or full (regular visits and attendance at casting stages).
  • Mandatory inspection points the contractor may not pass without the supervisor's approval.
  • Number or frequency of visits.
  • Reports: their format and delivery timing.
  • Responsibility for submitting construction notifications on the platform.
  • Duration of supervision and what happens if the contractor is delayed.

How to choose an engineering supervision office

  1. An office accredited by the Saudi Council of Engineers with disciplines covering your project.
  2. A named site engineer who knows you and your project, not just a name on paper.
  3. Independence from the contractor: the supervisor represents you, so avoid the contractor nominating the supervisor.
  4. Proximity to the site and quick response to pre-casting inspection requests.
  5. Photo-documented reports sent to you after every visit.

Key inspection points in engineering supervision

StageWhat the supervisor checksWhy before proceeding?
Setting outGridlines and setbacks matching the drawings and survey reportAn error here accumulates through the whole building
ExcavationLevel and soil type compared with the soil reportFoundations were designed on specific assumptions
Footing and column reinforcementBar diameters, numbers and concrete coverAfter casting it cannot be seen
Formwork and slab reinforcementAlignment, reinforcement and openingsSlab errors are among the costliest
CastingAttendance, and taking concrete samplesConcrete quality is documented at casting time
InstallationsElectrics, plumbing and AC before closing upAfter plastering, repair means breaking
WaterproofingFoundations, roofs and bathroomsWater leakage is the most common complaint after moving in

Full or partial supervision? A comparison

ItemPartial supervisionFull supervision
AttendanceVisits at specific stagesRegular visits and attendance at all casting stages
Suitable forSmall projects with a trusted contractorVillas, apartment buildings and commercial projects
DocumentationReports on main stagesRegular photo-documented reports
RiskErrors between visits may passLower likelihood of errors passing

The owner's relationship with the supervisor and contractor

The supervisor represents you in front of the contractor. For this role to succeed:

  • Give instructions to the contractor through the supervisor or with their knowledge, so no undocumented changes arise.
  • Do not approve any on-site change before the supervisor's opinion and approval of the appropriate service on Balady if needed.
  • Read the reports and ask about any note you do not understand.
  • Link contractor payments to the supervisor's reports on stage completion.

Terms you need to know

TermShort meaning
BaladyThe unified digital platform for municipal services, replacing visits to municipal offices for construction licences
Balady BusinessThe platform interface for engineering offices and contractors, from which the office submits applications
Survey decision (survey report)A document defining the plot's boundaries and dimensions on the ground, issued for a specific purpose such as construction or demolition
Design officeThe engineering office that prepares the designs and submits the permit application
Supervising officeThe office that verifies construction matches the drawings and submits construction reports
Technical inspectorA body that reviews drawings as part of the hidden defects insurance procedure and issues the safety confirmation certificate at the end
Hidden defects insuranceA policy covering defects that appear after construction and were not visible at handover
Occupancy certificateThe building completion certificate confirming the building's actual completion

Engineering supervision with Abak

We supervise villa, apartment building and commercial projects in Riyadh: inspection before every casting, photo-documented reports, timely construction notifications, and following the occupancy path until the certificate is issued. If we are also the designer, the whole project is in one team's hands.

Contact us: 0531145777 | Abak Engineering Consultancy

Frequently asked questions

Can a building permit be issued without a supervising office?

No. Contracting a supervising engineering office and a building contractor is a requirement of the building permit issuance service on Balady.

What is the supervising office's link to the occupancy certificate?

For new applications, the occupancy certificate is issued through the supervising office after construction reports are submitted.

Can the supervising office be changed during construction?

Balady's Add and modify building components service allows selecting the supervising office or retrieving it from the insurance. To change the supervisor without a modification, check the procedure with the platform on 199040.

Is partial supervision enough?

It depends on project size, but at minimum make sure supervision covers foundations, the concrete frame and installations before they are closed up.

Who submits construction notifications on the platform?

The supervising office; once complete, the occupancy certificate path starts for new permits.

Is the supervisor responsible for the contractor's errors?

The supervisor is responsible for checking, documenting and stopping violations, the contractor for construction; the contract sets out the details.