Quick answer: Yes, the plans can be modified after the building permit is issued, but any change to the building's components must be approved before it is built through the "Add and modify building components" service on Balady, with the engineering office preparing the revised drawings. Building a change that violates the permit without approval exposes the owner to municipal penalties and blocks the occupancy certificate later.
The plan approved in the permit is your "contract" with the municipality on the shape of your building. During construction, natural wishes for change arise: a bigger room, an extra annex, or splitting units for rent. In this guide from Abak Engineering Consultancy we explain the types of plan changes, which need a permit modification, how to do it properly, and what happens if you do not.
Types of plan changes after the permit
| Type of change | Examples | Does it need a permit modification? |
|---|---|---|
| Adding a component | Rooftop annex, roof room, extra floor, external annex | Yes: Add and modify building components |
| Deleting a component | Cancelling the first floor, cancelling an annex | Yes: Add and modify building components |
| Structural change | Removing a column or load-bearing wall, enlarging a span, an opening in a slab | Yes, with revised structural design |
| Changing areas or use | Converting an annex into an apartment, changing the use of a part | Yes; the office determines the path |
| Dividing the building into units | Converting a villa into apartments or duplexes for rent | Yes; division contrary to the permit is an explicit violation in the penalties regulation |
| Façade changes | Changing openings, materials or projections | Depends on the effect on areas and requirements; consult the office |
| Interior finishes | Floors, paint, suspended ceilings, furniture layout | Usually do not affect the permit, but must comply with the building code |
The practical rule: any change to what is drawn on the approved plan in terms of components, areas, structural elements or uses needs approval before construction. If in doubt, ask the design office before the contractor starts.
How are plans modified properly?
Through the Add and modify building components service on Balady, which allows adding, modifying and deleting building components in the permit without visiting the authority. The steps:
- From the dashboard choose your user role, then "New application".
- Specify the owner type and applicant.
- Select the building permit whose components you want to modify.
- Select the design office or retrieve it from the insurance.
- Select the supervising office and contractor or retrieve them from the insurance.
- Send the application to the engineering office, which prepares the revised drawings and completes the data.
- Pay the fee invoice.
- The modified permit is issued and can be printed.
Cost details in our article: Building permit modification cost.
Modifying plans during construction: the right order
- Stop only the affected works, and let the contractor continue what is not affected.
- Notify the supervising office to document the site's condition before the change.
- Ask the design office to assess the change: does it affect the structure? Do the area's requirements (setbacks, ratios, heights) allow it?
- Submit the component modification request and wait for approval.
- Give the contractor the approved revised drawings and ask them to work from them exclusively.
- Keep both versions of the plan (original and modified), clearly marking the current one.
What happens if the change is built without approval?
1. Municipal penalties
The regulation on penalties for municipal violations covers construction that does not conform to the permit. Among the latest additions, in October 2025, is the violation of dividing a building into units contrary to the building permit, with penalties as published by the ministry:
- A fine of SAR 5,000 to 25,000 per violating unit.
- The violator must remove the violation at their own expense.
- If removal is structurally impossible because it would affect the building's safety: paying half the construction cost of the violating work, with correction and removal of harm, and submitting a certificate from a qualified engineering office accredited by the ministry proving the safety of the structures.
Each item in the penalties schedule has a specified correction period, as Balady explains.
2. A blocked occupancy certificate
The building completion certificate confirms the building's actual completion and, for new permits, is issued via the supervising office after construction reports. Any difference between the built building and the approved plan shows up here and stops the certificate until resolved. Read Building completion certificate requirements.
3. Effect on hidden defects insurance
The policy was issued on a design reviewed by the technical inspector. Building something different without approval weakens your position in any later claim. The correct path is approving the change through the service, which lets you retrieve the designer, supervisor and contractor from the same insurance.
4. The design office's responsibility
Saudi Building Code regulations hold the design office accountable for non-compliant drawings. For example, amendments to the code violations classification regulation announced in 2021 included a SAR 5,000 fine on the design office if it submitted drawings or designs violating the code and the permit was issued on them. So a serious office will not modify your plan "on paper" without verifying that the change complies with the code and requirements.
Changes owners often request and how they are handled
Adding a roof room
A component addition. First check the rooftop annex ratio allowed in your area and whether the existing roof can carry the load.
Converting the external annex into a separate rental apartment
A change of use that may approach "dividing the building into units". Do not build it before the office determines the legal path; this is exactly the violation whose penalty was tightened in 2025.
Merging two rooms by removing a wall
If the wall is load-bearing, it is a structural change requiring design and approval. If it is a non-load-bearing partition, it may not change the permit's components, but ask the office to confirm in writing.
Cancelling the first floor and keeping the ground floor
A component deletion through the same service. Details in Building permit modification cost.
Changing the façade design
If areas, setbacks and projections stay the same, the impact is usually limited. If projections or openings overlooking neighbours change, check the requirements. For ideas: Modern house façade design.
How to avoid needing to modify the plans at all
- Allow enough time for the design stage and review the plan with the whole family before submission.
- Think about the future: will you need an extra floor? A rental unit? Design them into the permit from the start.
- Ask for 3D images before approving the plan; paper drawings are deceptive when judging space.
- Choose an office that asks you the right questions. Read Architectural design office.
Modifying your plans with Abak
We review your permit, your approved plan and the change you want, and tell you clearly whether it needs a permit modification, whether the requirements allow it, and its structural impact. Then we prepare the revised drawings and handle the request on Balady until the modified permit is issued, coordinating with the contractor and supervisor so your site does not stop longer than necessary.
Contact us: 0531145777 | Abak Engineering Consultancy
Frequently asked questions
Can the plans be modified after the building permit is issued?
Yes, through the Add and modify building components service on Balady, with the engineering office preparing the revised drawings before construction.
Do I need to visit the municipality to modify the plans?
No, the service is electronic and allows adding, modifying and deleting components without visiting the authority.
What is the penalty for dividing a building into units contrary to the permit?
A fine of SAR 5,000 to 25,000 per violating unit with removal, or half the construction cost of the violating work if removal is structurally impossible, with a safety certificate from a qualified engineering office.
Do minor interior changes require a permit modification?
Finishes that do not change components, areas or structural elements usually do not affect the permit, but ask the engineering office to confirm before building.
Does modifying the plans affect the occupancy certificate?
Yes, the built building must match the approved modified permit, otherwise the certificate is blocked until resolved.
Who prepares the revised drawings?
The design engineering office you select in the request or retrieve from the insurance.
Official sources
- Add and modify building components service – Balady (Arabic)
- Okaz: building unit division added to the municipal penalties regulation, October 2025 (Arabic)