Short answer: The occupancy certificate confirms a building's actual completion and is issued through Balady's "Issue an occupancy certificate" service for existing buildings; Balady treats it and the building completion certificate as one service. After it is issued, a building compliance certificate is issued proactively. A key condition is a building permit issued 6 months or more ago with no occupancy certificate previously issued on it.
Key Points
- The occupancy certificate proves the building is actually complete.
- It is issued against an existing building permit on Balady.
- The permit must be at least 6 months old.
- The compliance certificate follows automatically, with no separate request.
- Old municipality permits must be transferred to Balady before applying.
Occupancy, Completion and Compliance Certificates: The Difference
| Certificate | What it proves | How it is issued |
|---|---|---|
| Occupancy / completion certificate | The building's actual completion according to its permit | Balady's issue an occupancy certificate service |
| Building compliance certificate | The building's compliance with requirements (visual distortion, visible safety) | Issued proactively after the occupancy certificate; there is also a separate service for existing buildings |
For more on completion, read our building completion certificate and completion certificate requirements and steps.
When Do You Need an Occupancy Certificate?
- After construction is completed and before living in or renting the building.
- To obtain a commercial licence for an activity in the building.
- When selling or arranging property finance.
- To connect some services or transfer them to the owner's name.
- When subdividing property units.
Conditions for Issuing an Occupancy Certificate
- A building permit exists on Balady.
- At least 6 months have passed since the permit was issued.
- No occupancy certificate has been issued on the same permit.
- The completed building matches the permit and approved drawings.
Steps to Issue an Occupancy Certificate
- Log in to Balady and choose the issue an occupancy certificate service.
- Select the building permit for which the certificate is required.
- Complete the required data and attachments.
- Pay the fees, then issue and print the certificate.
- The building compliance certificate is issued proactively afterwards.
Before You Apply: A Compliance Checklist
- Number of floors and annexes matches the permit.
- Setbacks and parking entrances are as drawn.
- The number of units has not changed and no unit has been split in two.
- Façades are complete with no visible visual distortion.
- Visible safety requirements are installed for buildings that need them.
- Parking spaces are provided in the required number.
Dividing Units Contrary to the Permit
One of the most common blockers is dividing a building into more units than the permit allows to increase income. The Ministry of Municipalities and Housing has announced penalties for dividing a building into units contrary to its permit of up to SAR 25,000 per unit plus removal. The right solution is modifying the permit before execution, not after. See modifying plans after a building permit.
Occupancy Certificates for Older Buildings
| Situation | Route |
|---|---|
| Old municipality permit | Transfer the permit to Balady, then apply for the certificate |
| Old occupancy certificate issued by the municipality | Issue a new version with the Balady logo |
| Building without a permit | Correct the building's status first |
| Building contrary to its permit | Modify the permit or correct the status |
Common Problems and Solutions
The permit is an old municipality permit
It must be transferred to Balady first. See old building permit not showing on Balady.
The building does not match the permit
An extra floor, annex or unit division contrary to the permit blocks the certificate. The solution is modifying the permit or correcting the status before applying.
The permit has expired and construction is not complete
Renew or extend the permit first.
An old occupancy certificate from the municipality
A new version bearing the Balady logo can be issued through the platform.
Occupancy Certificates with Abak Engineering Consultancy
We check the building's compliance with its permit before applying, resolve discrepancies through permit modification or status correction, and follow the application until the certificate is issued.
Contact us: Construction permit services | 0531145777
Frequently asked questions
What is an occupancy certificate?
A certificate confirming a building's actual completion, issued by Balady against the building permit.
Is the occupancy certificate the same as the completion certificate?
On Balady they are one service: issuing an occupancy certificate for existing buildings (building completion).
When can I apply for an occupancy certificate?
Once at least 6 months have passed since the building permit was issued, if no certificate has been issued on it before.
Do I need a separate request for the compliance certificate?
No. The building compliance certificate is issued proactively after the occupancy certificate is issued and the invoice paid.
Can an occupancy certificate be issued for a single unit?
The certificate is issued against the building permit; unit status depends on the permit and subdivision.
Does Abak follow occupancy certificate applications?
Yes, including compliance checks and resolving comments.