Quick answer: The building completion certificate is the same as the occupancy certificate on Balady: a certificate confirming the building's actual completion, issued by the competent authorities. Its fee is fixed under the Municipal Services Fees Regulation: SAR 200 for residential, SAR 300 for residential-commercial and SAR 400 for commercial. After it is issued, the building compliance certificate is issued automatically and the hidden defects insurance policy is activated.
Many people confuse the building completion certificate, the occupancy certificate and the compliance certificate, and find conflicting information about fees. In this article from Abak Engineering Consultancy we explain what the certificate is, why it matters and how it relates to the other certificates, based on Balady and the official fee regulation.
What is the building completion certificate?
Balady offers a service called "Occupancy certificate issuance", described as an electronic service for issuing an occupancy certificate for existing buildings (building completion) without visiting the authority. It defines the occupancy certificate as a certificate confirming the actual completion of buildings, issued by the competent authorities.
The Municipal Services Fees Regulation names the item "Building completion certificate (occupancy certificate)". So officially, the building completion certificate and the occupancy certificate are one document.
Completion certificate vs. compliance certificate
| Item | Completion (occupancy) certificate | Building compliance certificate |
|---|---|---|
| What does it prove? | The building's actual completion | The building's compliance with requirements |
| How is it issued? | On application via Balady (or via the supervising office for new applications) | Automatically (proactively) after the occupancy application is complete and its invoice is paid |
| Separate application? | Yes | No, it follows the occupancy certificate |
For existing buildings that need a compliance certificate through a different route, read our guide: Issuing a building compliance certificate.
Building completion certificate fees (official)
Under the Municipal Services Fees Regulation, the completion certificate fee is fixed for all municipality categories, so the fee in Riyadh is the same as in any governorate:
| Building type | Fee |
|---|---|
| Residential | SAR 200 per certificate |
| Residential-commercial | SAR 300 per certificate |
| Commercial | SAR 400 per certificate |
The fee is not calculated per square metre, unlike the building permit. To compare all municipal fees: Building permit fees 2026.
Why does the building completion certificate matter?
- It proves the building was actually completed as licensed, and is the last station in the building permit life cycle.
- It activates the hidden defects insurance policy: according to Balady, the policy is issued before the building permit and activated after the occupancy certificate is issued, when the insurer is notified. In other words, the owner's protection against hidden defects effectively starts with this certificate.
- It opens the way to the compliance certificate, which is issued proactively after it.
- It helps in property transactions such as sale and financing, as an official document proving the building's status.
The scale of use is shown by the Ministry of Municipalities and Housing's announcement that it issued more than 38,000 occupancy certificates for buildings and facilities in the first half of 2026.
When can the building completion certificate be issued?
Balady sets two routes:
- New applications: the occupancy certificate is issued through the supervising office after construction reports (construction notifications) are submitted.
- Previously issued (old) permits: by applying for the occupancy certificate service, provided the permit was issued 6 months or more ago and no occupancy certificate has been issued on it before.
Detailed requirements and steps in our article: Building completion certificate requirements and steps.
What blocks the building completion certificate?
- Differences between the built building and the permit: any addition or modification not approved through the Add and modify building components service. Read Modifying a building permit.
- No hidden defects insurance policy for buildings required to have one.
- Missing supervising office reports during construction.
- Outstanding municipal violations on the property.
The supervising office's role in the completion certificate
For new permits, the supervising office triggers the occupancy certificate path after submitting construction notifications. So the quality of supervision during construction determines how quickly you get the certificate. Read Engineering supervision office.
The building's journey to the completion certificate
| Stage | What happens | Relation to the certificate |
|---|---|---|
| Before the permit | Hidden defects insurance policy issued and drawings reviewed by the technical inspector | The policy is a later certificate requirement |
| Permit | Building permit issued with the approved design | The certificate will match the building against this permit |
| Construction | The supervising office follows up and submits construction notifications | Completed notifications trigger the occupancy path for new permits |
| End | The technical inspector issues the safety confirmation certificate once requirements are complete | A step before occupancy |
| Occupancy | Completion certificate issued and fee paid | The certificate itself |
| After | Compliance certificate issued proactively, and insurance activated | Automatic results of the certificate |
Completion certificates for old buildings
If your building was built years ago and no occupancy certificate was issued, it is in one of three situations:
- It has a permit issued 6+ months ago and matches it: apply directly for the occupancy certificate service.
- It has a permit but the built building differs: address the differences first via the Add and modify building components service.
- It has no permit: the path starts with a survey decision, then an existing building status-correction permit.
Old permits that do not appear on Balady have special handling. Read Old permits that do not appear on Balady.
What does the completion certificate usually include?
The certificate is an identification document for the building and usually includes the owner's details, building type, area, location, number of floors and the linked construction permit number. Any difference between this data and the building's reality shows up when applying.
Terms you need to know
| Term | Short meaning |
|---|---|
| Balady | The unified digital platform for municipal services, replacing visits to municipal offices for construction licences |
| Balady Business | The platform interface for engineering offices and contractors, from which the office submits applications |
| Survey decision (survey report) | A document defining the plot's boundaries and dimensions on the ground, issued for a specific purpose such as construction or demolition |
| Design office | The engineering office that prepares the designs and submits the permit application |
| Supervising office | The office that verifies construction matches the drawings and submits construction reports |
| Technical inspector | A body that reviews drawings as part of the hidden defects insurance procedure and issues the safety confirmation certificate at the end |
| Hidden defects insurance | A policy covering defects that appear after construction and were not visible at handover |
| Occupancy certificate | The building completion certificate confirming the building's actual completion |
Building completion certificates with Abak
If we are your project's supervising office, we submit construction reports promptly so the occupancy path is not delayed. If your permit is old, we inspect the building, match it against the permit and resolve differences before applying.
Contact us: 0531145777 | Abak Engineering Consultancy
Frequently asked questions about the building completion certificate
Is the building completion certificate the occupancy certificate?
Yes. The fee regulation calls it "Building completion certificate (occupancy certificate)", and the Balady service is named "Occupancy certificate issuance" for existing buildings (building completion).
How much is the building completion certificate fee?
SAR 200 for residential, SAR 300 for residential-commercial and SAR 400 for commercial, as a fixed fee per certificate.
Do I need to apply for the compliance certificate after occupancy?
No. The building compliance certificate is issued proactively via Balady after the occupancy application is complete and its invoice paid.
When does hidden defects insurance start?
The policy is issued before the building permit and activated after the occupancy certificate is issued.
Does the service require visiting the municipality?
No, it is offered electronically only via the Balady portal dashboard or mobile app.
Can a property be sold without a completion certificate?
The certificate is an official document proving the building's status and helps in sale and financing; it is best obtained before selling.
Do completion certificate fees differ between cities?
No, the fee is fixed for all municipality categories according to building type.