Quick answer: Obtaining a building permit in Saudi Arabia starts with an updated electronic title deed and a survey decision for construction purposes, then authorising a design engineering office through the Balady platform, contracting a supervising office and a contractor, and issuing a hidden defects insurance policy. After the technical inspector's review, the fees are paid and the permit is issued electronically for three years.
This guide is written from the owner's point of view: what you need to prepare, the decisions you make at each stage, and where owners usually get delayed. It was prepared by Abak Engineering Consultancy based on the procedures of the Balady platform and the Ministry of Municipalities and Housing.
Building permit requirements (official)
According to the building permit issuance service page on Balady, the application requirements are:
| # | Requirement | Practical note |
|---|---|---|
| 1 | Updated electronic deed from the Ministry of Justice, a housing contract or an investment contract | Paper deeds must be updated first |
| 2 | Survey decision for construction purposes | Issued by an authorised engineering office |
| 3 | Contract with a design engineering office | Prepares the drawings and submits the application |
| 4 | Contract with a supervising engineering office and a building contractor | Before issuance, not after |
| 5 | Hidden defects insurance for the building | Mandatory for residential and commercial before applying |
How to obtain a building permit: 8 steps for the owner
Step 1: Prepare the electronic deed
Make sure your deed is electronic and up to date with the Ministry of Justice. If it is a paper deed, this is your first step. Details in Updating paper deeds.
Step 2: Obtain the survey decision for construction
The survey decision (survey report) defines the plot's boundaries, dimensions and levels on the ground. The design office selects it on the platform when starting the permit application, so without it the application cannot even begin. You can authorise an engineering office to issue it via the Municipal Store app from the dashboard. See Abak's survey report service.
Step 3: Choose and authorise the design engineering office
From the Balady dashboard, choose your user role and authorise the design office. The office accepts the authorisation from its "Balady Business" account. Read our guide: Authorising an engineering office on Balady.
Step 4: Approve the design before submission
The office prepares the architectural and structural designs. This is the most important stage for you as an owner: review the space layout, façades and parking before submission. Any change after the permit is issued requires a separate service and additional cost.
Step 5: Contract the supervising office and contractor
Choosing the supervisor and contractor is a permit requirement. Hidden defects insurance is applied for by the building contractor via Balady Business after being authorised by the engineering office.
Step 6: Hidden defects insurance policy and technical inspection
The design office sends the application to the technical inspection company. According to Balady, the technical inspector reviews the drawings and designs as part of the insurance policy procedure. The policy is issued before the building permit and activated after the occupancy certificate is issued.
Step 7: Pay the fees
After approval a payment invoice is issued on Balady and paid via mada, Mastercard or SADAD. In Riyadh the fee is SAR 3 per square metre for residential buildings. Full table in Building permit fees.
Step 8: Receive the permit and keep the approved drawings
The permit is issued electronically and can be printed from the dashboard. Keep the approved drawings and ask the contractor and supervisor to work exclusively from them.
Checklist before you start
- ☐ The deed is electronic and updated in the current owner's name.
- ☐ No municipal violations are recorded on the plot.
- ☐ You know the permitted building type in the subdivision plan (residential, residential-commercial, commercial).
- ☐ You have decided the number of floors and annexes you want.
- ☐ You have an estimated budget covering office fees, soil investigation, hidden defects insurance and municipal fees.
- ☐ You have chosen an office accredited by the Saudi Council of Engineers.
- ☐ You have chosen a qualified contractor.
How long does obtaining a building permit take?
There is no single duration, because the permit passes through stages in which each party owns part of the time:
- You: preparing the deed and making design decisions quickly.
- The design office: preparing drawings and addressing comments.
- The technical inspector and insurer: review and policy issuance.
- The platform: issuing the invoice and permit after payment.
Balady notes that published service times do not include time spent completing missing items or processing by third parties. The fastest way to speed things up is a complete file from the start.
Reasons a building permit application is delayed or rejected
- An outdated deed or ownership data that does not match the survey decision.
- Violating the area's requirements: setbacks, building ratios or number of floors.
- Technical inspector comments on the structural design or non-compliance with the Saudi Building Code.
- The contractor's delay in applying for the insurance policy.
- The owner changing their mind about the design after submission, sending the application back to the start.
Special cases
Land you bought with a permit in the previous owner's name
You need the building permit ownership transfer service before proceeding. Read Transferring building permit ownership.
An old unlicensed building you want to modify
According to Balady, old buildings without permits apply for the existing building status-correction permit after a survey decision is issued for the same purpose.
An old permit that does not appear on Balady
See Fixing an old building permit that does not appear on Balady.
You want to change the design after the permit is issued
Through the Add and modify building components service. Details and cost in Building permit modification cost.
After obtaining the building permit: what next?
- Start construction under the supervising office. Read Engineering supervision office.
- The permit is valid for three years and can be extended annually for a fee.
- After completion, obtain the building completion certificate. Read Building completion certificate.
Practical scenarios: how the process differs by situation
Scenario 1: Vacant land with an electronic deed ready
The simplest case. Start directly by authorising the office to issue the survey decision, then design. Most of the time here goes into design decisions and technical inspection.
Scenario 2: Land with an old paper deed
Nothing starts before the deed is updated to electronic. Make this your priority, and ask the office to start gathering requirements and preliminary design at the same time so no time is lost.
Scenario 3: Land with an old building you want to demolish
You need a demolition permit first, which can be issued even if the building has no building permit, after a survey decision for demolition. Then a survey decision for construction, then the new permit. Read Demolition permits.
Scenario 4: Land shared among heirs
Confirm the authority of whoever will authorise the office on behalf of the owners, as the permit service refers to "the permit owner or their representative". Settling this legally before starting saves the application from stalling later.
Scenario 5: Land you bought with a valid permit in the seller's name
Transfer the permit's ownership instead of issuing a new one if the design suits you. Read Transferring building permit ownership.
Documents and decisions: what is required from you specifically?
| Stage | Required from the owner |
|---|---|
| Start | The electronic deed, and authorising the office from your Balady account |
| Design | Requirements list, approving options, and final written approval |
| Contracts | Signing the design office, supervisor and contractor contracts |
| Insurance | Coordinating with the contractor to apply for the policy on time |
| End | Paying the Balady invoice as soon as it is issued |
Everything else is done by the engineering office. If more is asked of you, ask why.
Terms you need to know
| Term | Short meaning |
|---|---|
| Balady | The unified digital platform for municipal services, replacing visits to municipal offices for construction licences |
| Balady Business | The platform interface for engineering offices and contractors, from which the office submits applications |
| Survey decision (survey report) | A document defining the plot's boundaries and dimensions on the ground, issued for a specific purpose such as construction or demolition |
| Design office | The engineering office that prepares the designs and submits the permit application |
| Supervising office | The office that verifies construction matches the drawings and submits construction reports |
| Technical inspector | A body that reviews drawings as part of the hidden defects insurance procedure and issues the safety confirmation certificate at the end |
| Hidden defects insurance | A policy covering defects that appear after construction and were not visible at handover |
| Occupancy certificate | The building completion certificate confirming the building's actual completion |
Obtain your building permit with Abak
We handle the entire path for you: survey decision, design, submission on Balady, and following up with the technical inspector until the permit is issued. We give you a schedule of the documents required from you from day one so the file is not delayed by missing items.
Contact us: 0531145777 | Abak Engineering Consultancy
Frequently asked questions
What are the requirements for obtaining a building permit?
An updated electronic deed or housing/investment contract, a survey decision for construction, contracts with a design office, a supervising office and a contractor, and a hidden defects insurance policy.
Can a building permit be obtained through the Balady app?
Yes. Authorisation, application tracking and payment are done electronically on the Balady platform or app via the National Single Sign-On, while the engineering office uploads the drawings from its account.
Who pays for hidden defects insurance?
The mandate falls on the building contractor, who applies for the policy via Balady Business, and its cost is usually passed through the construction contract.
Can I start building right after payment?
Start after the permit is issued and printed, under the supervising engineering office registered on the permit.
Can design start before the deed is updated?
You can start gathering requirements and preliminary design, but submission on Balady requires an updated electronic deed.
Do I need a new survey decision if I have an old one?
A survey decision is issued for a specific purpose; a building permit requires a survey decision for construction, and the office will determine whether your current one is valid.



