Quick answer: Building permit issuance is done entirely online through the Balady platform under "Construction Licences". The service allows issuing a building permit or a fencing permit and passes through four stages: authorising the design office, preparing and uploading the designs, technical inspection with hidden defects insurance, then payment and printing. The permit is valid for three years and can be extended.
Many owners confuse issuing a building permit with renewing or extending it, or a building permit with a restoration or modification permit. This guide from Abak Engineering Consultancy puts the picture in order: what types of construction licences exist on Balady, when you need each one, and how the stages of issuing a new building permit work.
What is a building permit?
A building permit is a municipal construction licence. The Implementing Regulations of the Municipal Licensing Procedures Law define a municipal licence as written approval from the municipality to a natural or legal person to build or open a shop on a specific site in accordance with the regulations, covering both commercial and construction licences. All of this is done through the unified electronic platform, "Balady".
Balady lists the service under several search terms, including: building permit, electronic building permit, new building permit, construction permit, construction licence, building modification permit and building extension permit. All lead to the Building permit issuance service.
Types of construction licences on Balady
| Service | When do you need it? |
|---|---|
| Building permit issuance | New construction on a plot, or building a wall (fencing permit) |
| Building permit renewal | An existing permit that needs renewal depending on its status |
| Building permit ownership transfer | Land ownership changed while the permit is in the previous owner's name |
| Add and modify building components | You want to add, modify or delete components in an existing permit |
| Building restoration permit | Repairing defects without adding components or changing structural elements |
| Building demolition permit | Demolishing an existing building |
| Existing building status-correction permit | An old unlicensed building you want to modify or regularise |
| Site preparation permit | Site preparation works before construction |
| Occupancy certificate issuance | After construction is complete (building completion) |
Each service has a separate guide on our site: Restoration permit, Demolition permit, Modifying a building permit, Transferring building permit ownership, Building completion certificate.
Stages of issuing a new building permit on Balady
Stage 1: Login and authorisation
- Log in to the Balady platform or app via the National Single Sign-On.
- Go to the dashboard and select your user role.
- The owner or their representative authorises a design engineering office to issue the building permit.
Stage 2: The design office prepares the application
- The office logs in to Balady Business, accepts the authorisation and starts the application.
- It selects the plot's survey report.
- It prepares the architectural and structural designs.
- It completes the application data, attaches files and agrees to the municipal undertakings.
Stage 3: Technical inspection and insurance
- The application is sent to the technical inspection company, which reviews the drawings as part of the hidden defects insurance procedure.
- The contractor applies for the hidden defects insurance policy, mandatory before the permit for residential and commercial buildings.
Stage 4: Payment and issuance
- The payment invoice is issued and paid electronically.
- The permit is issued and can be printed, and the application is tracked from "My requests and licences".
For the owner's perspective and a checklist, read How to obtain a building permit, step by step.
Building permit issuance requirements
- An updated electronic deed from the Ministry of Justice, a housing contract or an investment contract.
- A survey decision for construction. Survey report service.
- A contract with a design engineering office to design the drawings.
- A contract with a supervising engineering office and a building contractor.
- Hidden defects insurance for the building.
Industrial facilities have additional requirements. Read Factory building permits.
Permit validity and extension
According to the Municipal Services Fees Regulation:
- A building or wall construction permit is valid for three years from issuance.
- Extension: the fee is charged annually, each extension is one year, at the same rate per square metre as issuance.
Balady's building permit renewal service requires contracting an engineering office, paying the service fee, and holding an insurance policy if construction has not started and the building type requires insurance.
Building permit issuance fees
In Riyadh city (Category 1): SAR 3 per m² for residential, SAR 4 for residential-commercial, SAR 6 for commercial, and SAR 2 per linear metre for walls. The full table for all categories with calculation examples is in Building permit fees 2026.
Construction waste management as part of permit issuance
The ministry has approved requirements for disposing of construction, demolition and restoration waste. Among the most important: calculating estimated waste quantities during permit issuance and adding them to the permit via Balady, and undertaking to contract a licensed transporter and provide a waste container. For the environmental side read Construction and demolition waste management – Abak Green.
After the building permit is issued
- Supervision: the supervising office follows construction and submits construction reports. Read Engineering supervision office.
- Modification: any change to components is done via the Add and modify building components service.
- Completion: after completion the occupancy certificate is issued, followed proactively by the compliance certificate.
How do you choose the right construction licence service?
Choosing the wrong service means a rejected application and lost time. Use these questions to identify your service:
- Is there an existing building on the land?
- No → Building permit issuance (or a fencing permit for a wall only).
- Yes → go to question 2.
- Does the building have a building permit?
- No, and you want to keep and modify it → Existing building status-correction permit after a survey decision.
- No, and you want to remove it → Demolition permit after a survey decision for demolition.
- Yes → go to question 3.
- What do you want to do with the licensed building?
- Repair defects without additions or structural changes → Restoration permit.
- Add, modify or delete components → Add and modify building components.
- Remove it → Demolition permit.
- Construction is finished → Occupancy certificate.
- Has the land owner changed? → Building permit ownership transfer before any other service.
The building permit life cycle from issuance to closure
| Stage | Service or procedure | Note |
|---|---|---|
| Before construction | Survey decision → building permit issuance | With hidden defects insurance |
| During construction | Supervision and construction reports | Through the supervising office |
| If a change arises | Add and modify building components | Before construction, not after |
| If it takes longer | Permit extension | Annual fee |
| After construction | Occupancy certificate → compliance certificate | And insurance activation |
Understanding this cycle from the start lets you plan each stage before it arrives, instead of discovering its requirements late.
Terms you need to know
| Term | Short meaning |
|---|---|
| Balady | The unified digital platform for municipal services, replacing visits to municipal offices for construction licences |
| Balady Business | The platform interface for engineering offices and contractors, from which the office submits applications |
| Survey decision (survey report) | A document defining the plot's boundaries and dimensions on the ground, issued for a specific purpose such as construction or demolition |
| Design office | The engineering office that prepares the designs and submits the permit application |
| Supervising office | The office that verifies construction matches the drawings and submits construction reports |
| Technical inspector | A body that reviews drawings as part of the hidden defects insurance procedure and issues the safety confirmation certificate at the end |
| Hidden defects insurance | A policy covering defects that appear after construction and were not visible at handover |
| Occupancy certificate | The building completion certificate confirming the building's actual completion |
Issue your building permit with Abak
We are an accredited engineering office in Riyadh that handles building permit issuance on Balady from authorisation to printing, and continues with supervision until the occupancy certificate. We also handle complex cases: ownership transfers, old permits, status correction and modifications.
Call us: 0531145777 | Abak's services
Frequently asked questions
What is the difference between renewing and extending a building permit?
The regulation refers to extending the construction permit year by year for an annual fee, while Balady offers a "Building permit renewal" service with its own requirements. The engineering office determines the right service for your permit's status.
Does the building permit issuance service cover building a wall?
Yes, the service allows applying for a building permit or a fencing permit.
Do I need a building permit for a minor interior change?
Repairs without adding components or changing structural elements are done with a restoration permit. Adding or modifying components uses the Add and modify building components service.
Can a building permit be issued for an existing unlicensed building?
Old unlicensed buildings apply for the "Existing building status-correction permit" after a survey decision is issued for the same purpose.
Can a building permit be issued for a wall only?
Yes, the building permit issuance service allows applying for a fencing permit.
What is the site preparation permit service?
A separate service under construction licences on Balady for site preparation works; the engineering office determines whether your project needs it.
Official sources
- Building permit issuance service – Balady (Arabic)
- Building permit renewal service – Ministry of Municipalities and Housing
- Municipal Services Fees Regulation (Arabic)
- Implementing Regulations of the Municipal Licensing Procedures Law (Arabic)
- Requirements for disposing of construction, demolition and restoration waste (Arabic)